X and Y can do a piece of work in 20 days and 12 days respectively. X started th

Loading

โœช Choose the correct option.

X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone and then after 4 days Y joined him till the completion of the work. How long did the work last?

6 days
10 days
15 days
20 days