X can do a piece of work in 40 days. He works at it for 8 days and then Y finish May 21, 2022May 21, 2022 by Amish Rai โช Choose the correct option.X can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16 days. How long will they together take to complete the work?40/3 days15 days20 days26 days Submit Answer