if 12 men working 2 hours a day take 10 days to complete a job, how long will 8

Loading

โœช Choose the correct option.

if 12 men working 2 hours a day take 10 days to complete a job, how long will 8 men working 6 hours a day take to do the same work?

3 days
4 days
5 days
6 days