Choose the correct option.

The business advises during iteration 5

planning that they require changes to the system delivered in iteration

3. Of the following activities, which would need to be done first to

minimize the introduction of regression risk when this feature is

changed?

A. Review and update all manual and automated tests impacted by this change to meet the new acceptance criteria.
B. Write new manual and automated tests for the feature and add them to the regression test suite.
C. Automate all test cases from the previous iteration and add them to the automated regression test suite.
D. Increase the amount of test automation around the system to include more detailed test conditions.