A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the May 21, 2022May 21, 2022 by Amish Rai โช Choose the correct option.A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in:5 days6 days10 days21/2 days Submit Answer