A can lay railway track between two given stations in 16 days and B can do the s May 21, 2022May 21, 2022 by Amish Rai โช Choose the correct option.A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in:46/5 days47/5 days48/5 days10 days Submit Answer