A contractor  undertook a project to complete it in 20 days which needed 5

Loading

Choose the correct option.

A contractor  undertook a project to complete it in 20 days which needed 5 workers to work continuously for all the days estimated. But before the start of the work the client wanted to complete it earlier than the scheduled time, so the contractor calculated that  he needed to increase 5 additional  men every 2 days to complete the work in the time the client wanted it:

If the work was further increased by 50% but the contractor continues to increase the 5 workers o every 2 days then how many more days are required over the initial time specified by the  client.

0.679166666666667
0.63125
0.510416666666667
0.464583333333333

Leave a Comment