โœช Choose the correct option.

A project that is in the implementation

phase is six weeks behind schedule. The delivery date for the product is

four months away. The project is not allowed to slip the delivery date

or compromise on the quality standards established for this product.

Which of the following actions would bring this project back on

schedule?

A. Eliminate some of the requirements that have not yet been implemented
B. Add more engineers to the project to make up for lost work
C. Ask the current developers to work overtime until the lost work is recovered
D. Hire more software quality assurance personnel