George can do some work in 8 hours. Paul can do the same work in 10 hours while

Loading

โœช Choose the correct option.

George can do some work in 8 hours. Paul can do the same work in 10 hours while Hari can do the same work in 12 hours. All the three of them start working at 9 AM. while George stops work at 11 am,the remaining two complete the work,approximately when will the work be finished?

0.479166667
12 noon
12.30 PM
0.541666667