P can complete a work in 12 days working 8 hours a day.Q can complete the same work in 8 days working 10 hours a day. If both p and Q work together,working 8 hours a day,in how many days can they complete the work?

0.0875347222222222
0.0854861111111111
0.0430902777777778
0.125717592592593