The following list contains risks that have

been identif

Loading

Choose the correct option.

The following list contains risks that have

been identified for a software product to be developed. Which of these

risks is an example of a product risk?

A. Not enough qualified testers to complete the planned tests
B. Software delivery is behind schedule
C. Threat to a patient’s life
D. 3rd party supplier does not supply as stipulated