โช Choose the correct option.
The ratio of efficiency of A is to C is 5:3. The ratio of number of days taken by B is to C is 2:3. A takes 6 days less than C, when A and C completes the work individually. B and C started the work and left after 2 days. The number of days taken by A to finish the remaining work is: