There is a work which can be completed by A with 12 days and B by 18 days. A and

Loading

โœช Choose the correct option.

There is a work which can be completed by A with 12 days and B by 18 days. A and B works together for 3 days and B left. After that how many days for A to complete the work?

5 days
6 days
7 days
8 days