You are the test manager and you are about the

start the

Loading

Choose the correct option.

You are the test manager and you are about the

start the system testing. The developer team says that due to change in

requirements they will be able to deliver the system to you for testing 5

working days after the due date. You can not change the resources(work

hours, test tools, etc.) What steps you will take to be able to finish

the testing in time.

A. Tell to the development team to deliver the system in time so that testing activity will be finish in time.
B. Extend the testing plan, so that you can accommodate the slip going to occur
C. Rank the functionality as per risk and concentrate more on critical functionality testing
D. Add more resources so that the slippage should be avoided